Landfill Gas CDM Project

The landfill project operation goal is to establish itself as a global leader in recycling waste by promoting increase in waste treatment technical knowledge, facilitating dissemination and new technology development expansion.

Main facilities

  • Header Pipe(900, 1000, 1200A) 35.5KM → Landfill gas collection and transfer
  • Condensation Water Removal Well 168 Stations → Facility for removing condensation water in landfill gas
  • Incinerator 6 Stations (680㎥/Sec) → Landfill gas incinerator
  • Simple Incinerator 135 Stations → Landfill stench removal

Treatment Status

  • Holding Capacity 606.9㎥/Sec (878,256㎥/ Day)
  • Incinerator Treatment Capacity 240㎥/Sec (346,320㎥/ Day)
  • Power Generated 369.4㎥/Sec (531,936㎥/ Day)

Power Plant

  • Total 50MW : Mar. 2007

Treatment Process

    Treatment Process

Landfill gas is collected through the header pipe and unnecessary gas is treated in the incineration; and the remaining recyclable gas is transferred to be generated as power or collected and transferred to leachate treatment or boiler management facility.