Landfill Gas CDM Project
The landfill project operation goal is to establish itself as a global leader in recycling waste by promoting increase in waste treatment technical knowledge, facilitating dissemination and new technology development expansion.
Main facilities
- Header Pipe(900, 1000, 1200A) 35.5KM → Landfill gas collection and transfer
- Condensation Water Removal Well 168 Stations → Facility for removing condensation water in landfill gas
- Incinerator 6 Stations (680㎥/Sec) → Landfill gas incinerator
- Simple Incinerator 135 Stations → Landfill stench removal
Treatment Status
- Holding Capacity 606.9㎥/Sec (878,256㎥/ Day)
- Incinerator Treatment Capacity 240㎥/Sec (346,320㎥/ Day)
- Power Generated 369.4㎥/Sec (531,936㎥/ Day)
Power Plant
Treatment Process
Landfill gas is collected through the header pipe and unnecessary gas is treated in the incineration; and the remaining recyclable gas is transferred to be generated as power or collected and transferred to leachate treatment or boiler management facility.